Sunday, September 03, 2006



Building signage - 9/1/06


Installing "Y" logo on North wall - 9/1/06

Friday, September 01, 2006


Gym with game lines - 8/28/06


Exercise Studio - cushioned wood floor - 8/28/06


Main Hall ceramic tile floor - 8/26/06


Child Watch VCT floor - 8/28/06


Entrance seating - 8/28/06


Membership desk with track lighting - 8/28/06



Wellness Center desk - 8/28/06



Showers before addition of partitions - 8/28/06



Locker room floor and wall tile - 8/28/06

Thursday, August 24, 2006


Exterior lights and landscaping - 8/23/06


Gym floor prep for painting - 8/23/06


Lights and ductsock in Natatorium (pool now holding water) - 8/23/06


Natatorium Viewing Room - 8/23/.06


Handrails on ramp to Upper Hall - 8/23/06


Suspended ceiling near Donor Wall - 8/23/06


VCT, cabinets and counter tops in Kitchen - 8/23/06


VCT flooring in Multipurpose Room - 8/23/06


"Cloud" installed above doorways - 8/23/06

Friday, August 04, 2006



Gymnasium floor installation - 8/4/06


Installing counter tops - 8/4/06



Natatorium roof edge treatment - 8/4/06


Light fixtures in Main Hallway - 8/4/06



Lockers in Family Changing area - 8/4/06

Tuesday, August 01, 2006


Parking lot paving and striping nearing completion - 8/1/06



Gym lights operational - getting ready for wood floor installation - 8/1/06


Installing lockers - 7/31/06


North entrance - 7/28/06


Installing ceramic tile in restroom - 7/26/06


Crown Vetch planted on West and North banks - 7/26/06

Sunday, July 23, 2006


Looking NW - ready for paving - 7/21/06


Main Entrance from South - 7/21/06


South elevation - 7/21/06


Membership Services desk taking shape - 7/21/06


Rear doors and downspouts installed - 7/21/06


Roof installation progresses over Locker Rooms - 7/21/06


Installing floor tile in Wet Corridor - 7/21/06


Floor tile in Locker Room - 7/21/06

Monday, July 10, 2006


Aerial view looking NW - Photo credit to Paula Blangger



Aerial view looking NE - Photo credit to Paula Blangger