Sunday, November 27, 2005


Is this a pool or a ice rink? 11/25/05


Lateral riser ready to go - 11/25/05


Finishing pool wall - 11/22/05


Wellness Center entrance - 11/22/05


Pool wall concrete and locker room roof trusses - 11/22/05


Main hallway - 11/22/05


Making terminations at switching module - 11/22/05


Waterproofing, insulation and start of backfill - NE corner of Natatorium

Sunday, November 20, 2005


Looking NE - 11/18/05


Roof deck on Gymnasium - 11/18/05


Roof deck on Dance Studio - 11/18/05


Roof deck on main hallway - 11/18/05


Looking SSE - Locker room walls going up - 11/18/05


East wall of Natatorium & North wall of gallery - 11/18/05


Drains in locker room - 11/18/05


Exterior forms for pool walls, 80% complete - 11/18/05


Electric service conduits - 11/18/05


Switching module and pad for temporary transformer - 11/18/05


Electric service work started - 11/18/05

Monday, November 14, 2005


Looking NE - 11/11/05


Pool sump - 11/11/05


Pool wall interior forms - 11/11/05


Pool wall interior forms - 11/11/05


Roof trusses in main hallway - 11/11/05


Steel going up - 11/11/05

Wednesday, November 09, 2005


Looking SE - 11/9/05


Roof deck at Dance Studio ready to start - 11/9/05


Locker room walls continue - 11/9/05


Forming pool walls continues - 11/9/05


Viewing gallery at pool starting to take shape - 11/9/05


Plumbing the sump - 11/9/05


Trusses in Gym - 11/9/05


Starting wall forms in pool - 11/8/05


Digging for sump - 11/8/05


NE Corner near Natatorium - 11/8/05


First steel truss in Gym - 11/8/05


Steel trusses in Dance Studio - 11/8/05

Saturday, November 05, 2005


West wall at mechanical room going up - 11/4/05


Pool floor complete - 11/4/05


Making it look good! 11/4/05


Almost done - 11/4/05


Working into a corner? 11/4/05


Stiff concrete requires a lot of muscle! 11/4/05


Architects on site 11/4/05


Pumping concrete - 11/4/05


Pool - starting lower portion - 11/4/05


Pool floor - upper portion - almost done 11/4/05

Thursday, November 03, 2005


Looking SE - 11/3/05


Looking E through locker room area - 11/3/05


Dance studio floor poured - 11/3/05