Thursday, August 24, 2006


Exterior lights and landscaping - 8/23/06


Gym floor prep for painting - 8/23/06


Lights and ductsock in Natatorium (pool now holding water) - 8/23/06


Natatorium Viewing Room - 8/23/.06


Handrails on ramp to Upper Hall - 8/23/06


Suspended ceiling near Donor Wall - 8/23/06


VCT, cabinets and counter tops in Kitchen - 8/23/06


VCT flooring in Multipurpose Room - 8/23/06


"Cloud" installed above doorways - 8/23/06

Friday, August 04, 2006



Gymnasium floor installation - 8/4/06


Installing counter tops - 8/4/06



Natatorium roof edge treatment - 8/4/06


Light fixtures in Main Hallway - 8/4/06



Lockers in Family Changing area - 8/4/06

Tuesday, August 01, 2006


Parking lot paving and striping nearing completion - 8/1/06



Gym lights operational - getting ready for wood floor installation - 8/1/06


Installing lockers - 7/31/06


North entrance - 7/28/06


Installing ceramic tile in restroom - 7/26/06


Crown Vetch planted on West and North banks - 7/26/06